GPRS Overview

HRSA supports PEPFAR to deliver on its goal of an AIDS-free generation. The Office of Global Health implements the agency’s PEPFAR activities. HRSA’s work builds on the agency’s domestic and international experience and expertise by improving outcomes along the treatment and prevention cascade for people living with HIV. HRSA works with host countries and other key partners to assess the needs of each country and design a customized program of assistance, implemented through cooperative agreement Grantees, that fits within the host country’s strategic plan for HIV/AIDS and/or the health sector. HRSA takes measures of the effectiveness of these programs using Global Post Award Reporting System also known as GPRS. Currently, the GPRS module includes one financial report, known as the Obligation and Expenditure Quarterly Progress Report.

 

The programs have different funding types and funding purposes. The funding types obligated to cooperative agreement Grantees by the Office of Global Health at this time are:

    • Country Operational Plan (COP) / Regional Operational Plan (ROP): Funds for HIV/AIDS program activities that are disbursed to Grantees at the country/regional level (also known as Operating Units or OUs) based on their Country or Regional Operating Plan (COP/ROP).
    • Headquarters Operational Plan (HOP): Funds received for PEPFAR program activities that are disbursed to Grantees for implementation of special projects or activities at the central/headquarters level or across multiple OUs.
    • American Rescue Plan Act (ARPA): Funds for program activities that address the intersection of HIV/AIDS and COVID-19 needs that are disbursed to Grantees at the country/regional level and were special, one-time FY21/22 funds. (Note: No new obligations are occurring for this funding type.)

 

The GPRS consists of a Submission Module on the Grantee’s side, as well as the Review Module on the Project Officer’s (PO) side to submit and review the Obligation and Expenditure Quarterly Progress Report.


Note: Enter your expenditure data on the Obligation and Outlay Report. The report labels are being updated in 2024 from 'outlay' to 'expenditure.' 

Obligation & Expenditure Report

The Obligation and Expenditure Quarterly Progress Report is the report submitted by the Grantee post-award to report the dollar amounts expended for each funding source for each quarter throughout the period of performance for the award.

The Obligation and Expenditure Quarterly Progress Report currently requires the Grantees to report the total dollar amount approved by GHSD/PEPFAR for the funding cycle, the total dollar amount obligated by HRSA, the approved carryover amount, and the dollar amount expended for each quarter for the project period by Operating Unit or HOP project. The Obligation and Expenditure Quarterly Progress Report will calculate the pipeline by fiscal year based on the approved PEPFAR budget and expenditure entries. The Grantee should also enter information in the comment section to explain underspending or overspending, including information about pending invoices and other expended funds that are expected to post against the reporting quarter at a later date.

Users can see the Obligation and Expenditure Quarterly Progress Report broken down for each Funding Source as well as Summary Overview of dollar amounts spent for each funding source for an OU.

GPRS Submission Tasks

GPRS Submission module is the system through which the Grantee submits the Obligation & Expenditure Report for a quarter. Every quarter, the system creates a task for each Grantee to submit the Obligation and Expenditure Quarterly Progress Report. The task is created by the EHBs system at the end of the budget period quarter and is due within 30 days after the end of the quarter. 

Log in to the external EHBs.

Screenshot of the EHBs landing page showing the Applicant Grantee option

Select 'Tasks' from the top navigation bar. 

Screenshot of the EHBs top navigation bar showing the Tasks tab

Landing on the Pending Tasks - List page, identify the task – “Obligation and Expenditure Quarterly Progress Report” which is prefixed with “OEQ”, and select 'Start' or 'Edit' if you have already begun working on the Progress Report, under the Options column on the right side of the screen.

Screenshot of the Pending Tasks List page showing the Grant Submissions Progress Report task

You land on the Obligation and Expenditure Quarterly Progress Report Status Overview page. First, review what OE forms are already there from previous quarters and determine if any need to be deleted, if they are no longer active funding sources, and no longer have a balance of funds (these might be from previous grants that carried over and need to be deleted).

Then determine what funding sources need to be added because they are not in the current list for the report.

Screenshot of the Status Overview page showing the OE Forms section

From the Obligation and Expenditure Quarterly Progress Report page, select 'Funding Source Setup' from the left navigation menu or Funding Source Setup section on the right side of the page. 

Screenshot of the Status Overview page showing the Funding Source Setup options

Complete the information on the Funding Source Setup page to add a new funding source for the Obligation and Expenditure (OE) Forms. 

A. Use the drop-down lists to select the Funding Source, Operating Unit, and Implementing Mechanism. 

Note: Funding source combinations are automatically populated on the form if they were entered in previous quarters.

Note: Only one unique combination is valid for each funding source/OU/mechanism combination and must be validated by the system to allow the Obligation and Expenditure Quarterly Progress Report entries. The Mechanism ID is assigned by PEPFAR, except in the case of the HOP funded mechanism, which have Mechanism IDs designated by OGH and the PO must provide this information to the Grantee. The project name (under Operating Unit) for a HOP funding source should be verified with the PO.

      • Funding Source – Choose from dropdown list (COP/ROP/HOP/ARPA)
      • Operating Unit – Choose from dropdown list (country, central, or project name)
      • Implementing Mechanism - Choose Mechanism Name and ID from the dropdown list

B. Click 'Add' to add the new funding source.

C. Click 'Delete' in the Action column to remove a Funding Source if it is no longer applicable.

D. Add additional Funding Source Details as needed and after entering all Funding Sources, click 'Continue' to save the information. 

Screenshot of the Funding Source Setup page

To work on the forms, from the Obligation and Expenditure Quarterly Progress Report Status Overview page, select the report you wish to edit from the left navigation menu or OE Forms section. 

You can view the status for each form next to the form name on the left navigation menu or the Status column in the OE Forms section. 

    • Red x (screenshot of the red x) indicates the form is not started
    • Blue exclamation mark (Screenshot of the Blue exclamation mark)  indicates the form is in progress
    • Green check mark (Screenshot of the Green checkmark) indicates the form is complete

Screenshot of the Status Overview page showing Forms in not started status

On the Form Page refer to the instructions at the top of the Obligation and Expenditure table for information about completing the table.

A. Provide the number values (whole integers and no decimals) for funding information and expended amounts across the relevant funding cycles and fiscal quarters and years. Fields, except for the last row, can be left blank if there is not data to report. You must enter a "0" in all of the fields of the last row, even if it is not a year that you need to report on, as these fields cannot be blank or you will receive an error message.

Note: Data is automatically populated on the form if it was entered in previous quarters. Please review this data and make any necessary updates to expenditures, approved budget, HRSA obligated, and approved carryover.

B. Use the Comments field to add notes about the data.

C. Select 'Save and Continue' at the bottom right of the screen. If all required fields contain valid data, the form status updates to Complete. You will receive an error message if there is any missing data. Select Save to save your work and continue working on the report at a later date.

Note: After clicking Save and Continue, if you have multiple OE forms, you will land on the next form to complete. You can also select additional OE forms from the Status Overview page. 

Screenshot of the OE form showing data entry section, Comments section, and Save and Continue button

Landing back on the Status Overview page, once you verify the data for each form is correct and all OE forms are in Complete status, select 'Submit Progress Report' under the Submit and Print section on the bottom right of the screen.

Screenshot of the Status overview page showing the Submit Progress Report option

On the Submit Report - Confirm page, you must:

A. Click the box to certify that the report is filled out accurately to the best of your knowledge

B. Click 'Confirm' to submit your report

Screenshot of the Submit Report Confirm page

Deadline Extension Request

You can request a due date extension from the Obligation and Expenditure Quarterly Progress Report Status Overview page or the Submissions Incomplete List. You must submit the extension request before submitting the progress report, or the option to request an extension is no longer available. You can submit the progress report while the extension request is pending, and if the request is approved, the due date is automatically updated. 

Request Deadline Extension from the Status Overview Page

If the report due has passed, the Status Overview page and Submit Report Confirmation page displays a note at the top with the option to request a deadline extension. Select the Click here option in the note and complete the extension request form. 

Screenshot of the Status Overview page showing the deadline extension request option at the top Note section

Screenshot of the Submit Report Confirm page showing the deadline extension request option in the Note section

Complete the extension request form. 

A. Enter the requested date in the Extension Date field.

B. Add Comments explaining the reason for the extension request.

C. Select the Submit to HRSA button to send the request for approval.

Screenshot of the Submissions Extension Request page

Request Deadline Extension from the Submissions Incomplete List

To request a due date extension for the OE report, select Submissions from the Tasks tab. 

Screenshot of the EHBs top navigation bar showing the Tasks tab with the Submissions option

On the Submissions - Incomplete List, find the Obligation and Expenditure Quarterly Progress Report task.

A. Expand the arrow next to the Due In column to view if an extension has already been requested and the approval status.

B. Expand the arrow in the Options menu and select Request Extension from the dropdown menu. 

Screenshot of the Submissions Incomplete List showing the Request Extension option

Complete the extension request form. 

A. Enter the requested date in the Extension Date field.

B. Add Comments explaining the reason for the extension request.

C. If an extension request was previously submitted, you can view the details in the History of Extension section.

D. Select the Submit to HRSA button to send the request for approval.

Screenshot of the Submission Extension Request page


  • No labels